Capital Projects

**CONSTRUCTION NOTICE**

Ridgeview Drive (Alma through Stacy) - Project began October 3, 2014. Adjacent neighborhoods may be affected with detours and construction signage. Construction will continue through July 2015.

The Engineering Department has been implementing projects from the 2008-2012 Capital Improvement Program, in the area of public infrastructure (roads, utilities and drainage). The ever-increasing challenges of a thriving and growing community have necessitated improvements in all categories.
  1. ROADS
  2. Utilities
  3. Facilities
  4. Future
  5. Maps
Lanes.png Alma Drive Widening
(Bethany to SH 121) 
Project Manager: Tim Porter

Montgomery Extension Montgomery Boulevard Extension
(Bethany to US 75)
Project Manager: Kevin Bates                 

  • Construction anticipated to be complete March 2016.
  • Portion of Montgomery Boulevard will be built by Developer
Ridgeview (Alma through Stacy) Ridgeview Drive, Phase 1
(Alma through Stacy)
Project Manager: Kevin Bates        
  • 4 lane divided roadway connecting existing 2 lane roadways
  • Construction completion anticipated Fall 2015
Stacy Road Stacy Road
(Greenville Ave to FM 1378)
Project Contact: Tim Porter
 
  • TxDOT project currently in design
  • Utility Relocations Underway
  • Construction Start - Anticipated Fall 2015       
US 75 US 75
(Spring Creek Pkwy to Collin County Line)
Project Contact: Chris Flanigan
Planning continues on this important roadway segment as the communities of Allen, Anna, Melissa, Fairview, McKinney and Plano look towards the ultimate improvement of this roadway, with 8 main lanes and HOV lanes. 

  • TxDOT project adding 2 additional lanes and ramp improvements.
  • Construction estimated to be complete January 2017