May 11, 2017 10:06 AM

Portion of Ridgemont Drive Closed

A portion of Ridgemont Drive from the existing railroad line to approximately 301 Ridgemont will be closed to all traffic beginning Monday, May 15.

The road closure will enable the reconstruction of the road and the implementation of a new culvert at the creek crossing. Due to the nature of the work involved, full road closure is necessary to optimize the safety of the work crews and public. Access to US 75 Frontage Road and Greenville Avenue will be impacted during this time.

During closure, traffic will be required to use alternate routes such as Bethany Drive or Legacy Drive. Updates will be provided through onsite message boards as well as through these road construction alerts. Make sure to subscribe at Alert Center Notify Me.

Click on the image below to enlarge.

Ridgemont Drive closure image

Facebook Twitter Google Plus Email

Latest Update:

October 13, 2017 10:21 AM

Ridgemont is expected be open to traffic by the end of the year, weather permitting.