Residents of two Allen subdivisions will soon enjoy some smoother streets.
The City has chosen a contractor to apply a micro-seal to streets in Walden Park Estates and Fountain Park Phase 2. The seal is applied in a thin layer to cover minor defects and extend the pavement life five to eight years. City crews have repaired damaged curbs and inspected the roadway surface for failed sections. City Crews will also be applying a crack sealer to the roadway surface prior to the micro-seal.
Walden Park Estates will receive the micro-seal on portions of W. Concord Lane, Concord Lane, E. Concord Lane, Walden Court, Roaring Springs Drive, Emerson Drive, New Bedford Lane and High Meadow Drive. This treatment is part of the city’s yearly maintenance program.
Fountain Park Phase 2 subdivision will receive the micro-seal on portions of Sycamore Creek Road, Autumn Lake Drive, Pebblebrook Drive and Roaring Springs. The micro-seal will represent the final roadway restoration of the neighborhood’s water and sewer rehabilitation project. Expected completion is July 2017.